| Azeri-Chirag-Gunashli
(ACG) contract signed |
Sept1994 |
| Chirag
development drilling |
August
1997 |
| Chirag
First Oil |
November
1997 |
| Supsa
pipeline operational |
February
1999 |
| Water
injection project |
1999 |
| Chirag drilling
technology upgraded |
2000 |
| ACG Phase 1 Full
Field Development |
August 2001 |
| Azeri subsea
drilling template |
June 2002 |
| ACG Phase 2 Full
Field Development |
Sept 2002 |
| Chirag and Sangachal
Terminal upgrade |
March 2003 |
| Chirag
- 200 million barrels |
May
2003 |
| West
Azeri template installed |
May
2003 |
| Central
Azeri Living Quarters arrive in Baku |
July
2003 |
| Central
Azeri drilling modules arrive in Baku |
Sept
2003 |
| Central
Azeri jacket completed |
December
2003 |
| Central Azeri
drilling modules arrive in Baku |
February 2004 |
| Central Azeri
jacket completed |
March 2004 |
| East Azeri Pre-Drilling
Program begins |
June 2004 |
| Central Azeri
Gas pipeline installed and platform launched |
July 2004 |
| Chirag - 250
million barrels |
August 2004 |
| West
Azeri Platform drilling modules arrive in Baku |
August
2004 |
| Central
Azeri Production, Drilling and Quarters Platform installed |
October
2004 |
| Central
Azeri Production starts |
February
2005 |
| Azeri
oil export starts |
March
2005 |
| West
Azeri production, drilling and quarters platform launched |
May
2005 |
| Central Azeri
casing-head gas delivered |
May 2005 |
| Chirag - 300
million barrels |
June 2005 |
| East Azeri drilling
modules and quarters platform arrive in Baku |
June 2005 |
| Central Azeri
C&WP platform topsides launched |
July 2005 |
| West Azeri topsides
installed |
Sept 2005 |
| Deepwater
Gunashli Pre-Drilling Program starts |
December
2005 |
| West
Azeri production starts |
January
2006 |
| East
Azeri platform launched |
March
2006 |
| C&WP
injects first gas |
May
2006 |
| Deep-water
Gunashli drilling modules and quarters in Baku |
June
2006 |
| East
Azeri topsides installed |
July
2006 |
| East
Azeri production began |
October
2006 |